Chelmsford Demolition, Teviot Avenue Redevelopment, Essex

In Winter 2025/2026, Windsor Waste Management partnered with Chelmsford Demolition to deliver a high-volume, time-critical asbestos waste disposal solution at the Teviot Avenue redevelopment in Aveley, Essex.
Category

Demolition

Client

Chelmsford Demolition

Location

Aveley, Essex

Date

December - January 2026

Project Details

In Winter 2025/2026, Windsor Waste Management partnered with Chelmsford Demolition to deliver a high-volume, time-critical asbestos waste disposal solution at the Teviot Avenue redevelopment in Aveley, Essex.

The regeneration scheme will replace three ageing blocks of 1950s non-traditional council flats with 48 new affordable homes, providing improved living standards for residents and supporting long-term community development.

Across an 8-week period between December and January, Windsor Waste Management removed 539 tonnes of asbestos-contaminated material using forty-seven 20-yard bins, all while maintaining a strict two-per-day exchange strategy to maintain the demolition works schedule.

Critically, this project also marked the successful trial of Windsor Waste Management’s new 20-yard asbestos container bags – an innovation designed to improve site efficiency, safety, and compliance across the demolition sector.
Awesome Image

Project Background

Teviot Avenue forms part of a transformational redevelopment initiative led by Thurrock Council to modernise outdated housing stock built using non-traditional construction methods in the 1950s. The original buildings contained cement bonded asbestos within structural elements and surrounding materials. As demolition progressed, significant volumes of hazardous materials were generated, including:

• Soil contaminated with cement bonded asbestos
• Concrete and rubble contaminated with cement bonded asbestos
• Cement bonded asbestos sheets

Chelmsford Demolition required a disposal partner capable of matching production output daily - without delays, without compliance risk, and without storage bottlenecks on site. With demolition already underway since August 2025, the waste disposal phase during winter presented both logistical and environmental challenges.
Awesome Image

Initial Planning & Coordination

Given the projected waste volumes and compressed timeframe, early coordination between Chelmsford Demolition and Windsor Waste Management was critical.

Key planning considerations included:
• High Daily Waste Output: The site required two 20-yard asbestos bins exchanged every day.
• Winter Working Conditions: Operations took place during December and January, requiring careful route planning and contingency scheduling to avoid weather-related disruption.
• Segregated Disposal Streams: Contaminated soil required specialist treatment prior to final disposal, while asbestos-contaminated rubble and bonded materials were directed to licensed hazardous landfill facilities.
• Compliance Assurance: All collections required full hazardous waste consignment documentation, ADR-compliant transport, and strict adherence to duty of care obligations.

To ensure responsiveness, Chelmsford Demolition’s site team maintained direct communication with their Windsor Waste Management Account Manager, enabling real-time scheduling adjustments where required.

Execution of Asbestos Disposal

Logistics and Container Management:

  • A total of forty-seven 20-yard bins were delivered, exchanged and removed over the 8-week period.
  • A structured exchange strategy scheduled two bin movements per day.
  • Transport planning ensured vehicles were routed efficiently to maintain uninterrupted demolition works.

Waste was sealed and secured in accordance with hazardous waste regulations prior to leaving site, eliminating risk of fibre release during transit.

Innovative Product Trial: 20 yard Asbestos Container Bags

A key differentiator on this project was the trial of Windsor Waste Management’s new 20-yard asbestos container bags, developed specifically to improve safety, compliance and operational efficiency within the demolition industry.

Traditionally, asbestos containers are lined with polythene and, once filled, manually enveloped and sealed. This process can be time-intensive and labour-heavy, as well as susceptible to inconsistent sealing standards.

The new 20-yard asbestos container bag system provides a purpose-designed, compliant containment solution that:

  •  Saves Significant Time on Site: The integrated bag design reduces manual lining and enveloping time, allowing demolition teams to maintain productivity, particularly critical when operating to a two-exchange-per-day schedule.
  •  Enhances Security and Containment: The engineered bag system provides a more consistent and secure method of sealing compared to traditional lining methods, reducing risk of fibre escape and improving containment integrity during transport.
  •  Improves Compliance Confidence: With a controlled, standardised containment solution, contractors gain added assurance that waste is packaged in accordance with regulatory requirements before leaving site.

Chelmsford Demolition’s trial demonstrated that the container bag system is not only practical under high-volume conditions but also particularly suited to fast-paced demolition projects.

This innovation represents a significant step forward for the demolition industry, combining safety, efficiency and compliance into a single, scalable solution.

Waste Segregation & Disposal
  • • Contaminated soil was transported to specialist treatment facilities
  • • Concrete, rubble and cement bonded asbestos were transported to licensed hazardous landfill.

 

Each load was tracked and documented, ensuring complete traceability and environmental compliance throughout the project lifecycle.

Project Outcome & Compliance

The Teviot Avenue asbestos disposal project was completed safely, compliantly, and on schedule.

Key Achievements:

  • • 539 tonnes of hazardous material removed
  • • 47 containers managed across an 8-week winter schedule
  • • Full regulatory compliance maintained with complete waste audit trail
  • • Successful real-world trial of the 20-yard asbestos container bag system
  • • Full regulatory compliance maintained with complete waste audit trail
  •  

The ability to sustain high-frequency bin movements while simultaneously trialing and validating an innovative containment solution demonstrates Windsor Waste Management’s commitment to continuous improvements within the demolition sector.

"Windsor Waste provided a first-class service for the disposal of ACM’s from both the structures and contaminated substructures playing a key role in returning a hazard free site for our client. Our client relationship executive Cerys Barrett was always available to ensure off & onsite project management was delivered as efficiently as possible during some tough winter conditions. We will definitely look to partner with Windsor Waste Management on all future projects and are currently in procurement discussions for other large scale asbestos disposal projects. Windsor Waste provide a professional and good value for money service, and we would recommend using their services to other companies within our industry."
Chelmsford Demolition
James Bailey
Director, Chelmsford Demolition

Conclusion

The Teviot Avenue redevelopment exemplifies the importance of partnership in high-volume, time-sensitive demolition works.

By working closely with Chelmsford Demolition’s operational requirements, Windsor Waste Management ensured that hazardous waste disposal aligned seamlessly with high-pressure project demands.

Moreover, the successful implementation of the new 20-yard asbestos container bag system highlights Windsor Waste Management’s proactive investment in innovation.

When managing over 500 tonnes of asbestos-contaminated material in winter conditions within eight weeks, success depends on:

  • • Proactive communication
  • • Logistical precision
  • • Compliance-first processes
  • • Operational agility
  •  

This project reinforces Windsor Waste Management’s position not only as a trusted disposal partner, but as an industry innovator driving safer, smarter asbestos waste solutions for demolition contractors across the UK.

More about Chelmsford Demolition

Chelmsford Demolition is an experienced demolition contractor delivering safe, efficient and environmentally responsible demolition services across commercial, residential and industrial sectors. Their team combines technical expertise with a strong focus on project delivery and health & safety compliance.

Get in touch for support with your next asbestos project!

T: 01708 55 99 66
E: enquiries@winwaste.com

Awesome Image
Number of
movements
0+
Awesome Image
Amount of tonnage
dealt with per year
0+
Testimonials

Happy Customers

Our Services

Providing comprehensive solutions and support services whatever your requirements

DGSA Service

DGSA Service

Partnering with a DGSA is a legal requirement for companies dealing with dangerous goods. If you’re looking for professional DGSA services, we can help point ...

DGSA Service

Partnering with a DGSA is a legal requirement for companies dealing with dangerous goods. If you’re looking for professional DGSA services, we can help point ...

Asbestos Disposal

We have a wealth of experience and reputation in asbestos disposal. An immediate response, nationwide with a personal and professional service.

Asbestos Disposal

We have a wealth of experience and reputation in asbestos disposal. An immediate response, nationwide with a personal and professional service.

Subscribe to our regular updates today

    About Windsor Waste Management

    Company registered in England No: 04081179

    Registered Address:
    Unit 29 Childerditch Industrial Estate
    Childerditch Hall Drive
    Little Warley
    Brentwood
    Essex
    CM13 3HD

    Part of the Windsor Integrated Services Group Limited

    Contact Us

    © Copyright Windsor Waste Management Limited 2024
    Built by Attract & Engage – Growth Marketing Agency
    Privacy PolicyCookie PolicyTerms & Conditions